How to Disconnect Power for Demolition or a Re-Roof

Published 2026-11-27

To disconnect power for a demolition or re-roof in NSW, you book a Level 2 Accredited Service Provider to make the supply dead at the point of attachment, the street pole or the pillar. A re-roof uses a temporary disconnection that is reconnected afterwards. A demolition needs a permanent disconnection and meter removal, arranged before the house comes down.

Switching off the main switch is not enough for either job. This guide explains why, how the two types of disconnection differ, and what to organise so the roofer or demolition crew is not left waiting.

Why does a re-roof or demolition need the power disconnected?

Because the parts of the supply that stay live with the main switch off are exactly the parts roofers and demolition crews work closest to. On an overhead supply, the service line runs from the street pole to a bracket on the fascia or a raiser bracket poking through the roof. That line is live all the time, and on many Sydney homes it sits right where the old roof sheets or tiles come off.

A demolition goes further. The machine pulls down the wall holding the meter board, and with it the consumer mains that run from the point of attachment to the main switch. Those cables are live up to the main switch whether the house is occupied or not, so they have to be made dead at the network side before anyone starts pulling the building apart.

SafeWork NSW's code of practice for work near overhead power lines sets minimum approach distances that ordinary workers cannot cross. A roofer cannot do the job properly while staying clear of a live service line on the roof, which is why the line is disconnected instead.

Do you always need a disconnection for a re-roof?

Not always. It depends on how the power reaches the house and how close the roof work gets to it. The common cases:

  • Overhead supply attached to the roof or fascia. Almost always disconnected, because the line and its bracket sit in the work zone and the bracket may have to come off to replace the roofing around it.
  • Overhead supply attached to a wall, well below the roof line. Sometimes not needed. The roofer and the electrician can judge it on site against the approach distances.
  • Underground supply from a pillar or pit. Usually no network disconnection, since nothing live crosses the roof. Roof-mounted gear such as solar panels, antennas and air conditioning still needs isolating before it is moved.

Repainting the fascia or eaves around the point of attachment raises the same question, and the same Level 2 disconnection solves it.

Temporary or permanent disconnection: what is the difference?

A temporary disconnection is undone when the trade work finishes, while a permanent one ends the supply to that building for good. They involve different people and different lead times:

QuestionTemporary (re-roof, repaint)Permanent (demolition)
Who does the workA Level 2 ASPA Level 2 ASP, with the retailer and metering provider
What happens to the meterStays in place, re-sealed after reconnectionRemoved by the metering provider
Electricity accountStays openClosed through your retailer
Getting power backReconnected once the roof is doneA new connection, often a temporary pole for the build
Typical noticeBook alongside the roofer's start dateSeveral weeks, because more parties are involved

Who is allowed to disconnect the power?

Only a Level 2 Accredited Service Provider can disconnect and reconnect a property from the Ausgrid or Endeavour Energy network. A roofer cannot do it, and neither can an electrician who holds only a standard licence, because the service line and the connection to it are network assets. Our guide to Level 1 vs Level 2 electricians sets out exactly where that boundary sits.

The Level 2 ASP also breaks and re-seals the meter, notifies the network that the work happened, and lodges a CCEW certificate of compliance where one is required. DM Electrical is Level 1 and Level 2 ASP accredited with both Ausgrid and Endeavour Energy, so the disconnection, any repair to the point of attachment and the reconnection are handled by one contractor through our Level 2 ASP service.

Roofer or demolition crew booked?

DM Electrical handles temporary and permanent disconnections across the Northern Beaches, North Shore, Eastern Suburbs and greater Sydney. Based in Brookvale, Level 2 ASP accredited.

Call 0410 144 047 Request a Quote

How does a temporary disconnection for a re-roof work?

It is usually two short visits a few days apart, with the house off the network in between. The usual order:

  1. Lock in the roofer's start date, then book the disconnection for that morning.
  2. The Level 2 ASP disconnects the service line, makes it safe and, where the roofing requires it, takes it off the bracket.
  3. The roofer replaces the roof around the point of attachment.
  4. The ASP checks the bracket and its fixing. If the fascia or raiser bracket was replaced, it has to be fixed back securely and keep the service line at the required height.
  5. The ASP reconnects the line, tests the installation, re-seals the meter and notifies the network.

The house has no power between those two visits, so plan for the fridge, freezer, alarm system and anyone working from home. If the old meter board is asbestos or the bracket is rusted through, a re-roof is a sensible time to deal with it, since the supply is already off. Our guide to asbestos meter board replacement covers the board side.

How do you disconnect power before demolishing a house?

Start with your electricity retailer, then book the Level 2 ASP, and leave several weeks before the demolition date. In sequence:

  1. Tell your retailer the building is being demolished and ask for a permanent disconnection and meter removal.
  2. If the builder needs power on site, organise a temporary power pole so it can be connected before or alongside the old supply coming off.
  3. The Level 2 ASP disconnects the supply at the street pole or the pillar and removes or makes safe the service line, so nothing on the old building is connected to the network.
  4. The metering provider removes the meter.
  5. Get written confirmation of the disconnection. Demolition contractors, and often council conditions, want evidence that services are off before work starts.

Gas, water and telecommunications have their own disconnection processes, so run them in parallel. If the rebuild will move an overhead supply underground, plan that with the new connection rather than the demolition. Our Church Point undergrounding project shows what that work involves.

What goes wrong when the disconnection is left late?

Most problems come from booking the electrician after the roofer or demolisher has already set a date. What we see most:

  • Crew on site, supply still live. The roofer cannot start near the line, and you pay for a wasted day.
  • Meter still on the wall at demolition. The retailer and metering provider run on their own timelines, which is why permanent disconnections need the longest lead time.
  • Bracket damaged during the re-roof. The line cannot go back up until the point of attachment is repaired, which adds time without power.
  • No site power for the build. The old supply comes off with nothing in its place, so tools run on generators until a temporary pole is connected.

Frequently asked questions

Can I just turn off the main switch for the roofers?

No. The main switch only cuts power to the circuits after it. The service line, the meter and the consumer mains between the street and the main switch stay live, and on an overhead supply that is the part closest to the roof.

How much notice do I need to disconnect power?

For a temporary disconnection, book it when the roofer confirms a start date. For a permanent disconnection before demolition, allow several weeks, because the retailer and the metering provider both have to act as well as the Level 2 ASP.

Does a re-roof need a disconnection if my power is underground?

Usually not for the supply itself, because nothing live crosses the roof. Solar panels, antennas and air conditioning units on the roof still need isolating before they are moved.

Will I have power while the roof is being replaced?

Not after a temporary disconnection. The house is off the network from the first visit until reconnection, which is usually a few days, so plan for refrigeration, alarms and anyone working from home.

The bottom line

A re-roof needs a temporary disconnection and a demolition needs a permanent one, and both are Level 2 ASP work. Book it before the crew arrives, and for a demolition start with your retailer weeks ahead. If you have roof or demolition work coming up, get in touch and we will line up the disconnection with your trades.

Related Guides

Ready When You Are

Call DM Electrical or send us a quick message. We respond fast.

Contact Us
4.9 (68)
  • L
    Linda Mapledoram
    3 months ago

    Have been using the company while renovating a kitchenette and general updates throughout the premises. Found the service positive in response to all requests and prompt in delivery. Highly recommend.

  • R
    Raymond Lambie
    7 months ago

    Shaun was great. Replaced our fuse box and installed a smart meter. He was a pleasure to deal with and took the time to explain everything to us. Very happy with the job DM Electrical did.

  • V
    Vic Gigliotti
    a year ago

    We had a power outage across half our office and couldn't find the issue. DM sent an experienced electrician who solved it within 20 minutes. Extremely professional, clean and efficient. We can't recommend Dan and the team highly enough.

  • T
    Tracey Hollings
    a year ago

    The team were punctual, polite and very efficient. Did an excellent job, which was a challenge considering the damage involved. They also did a great tidy up job. Left no mess. Highly recommend the team.

  • L
    Lewis Haines
    10 months ago

    Dan and his team of highly qualified tradesmen did the level 2 change over of our electrical mains. The service, attention to detail, communication and speed is unparalleled to any electrical service I have had.

  • C
    Claudine Athas
    a year ago

    Within an hour Dan sent the team to sort my urgent outage at work. He was kind, empathetic and professional. The problem was fixed and new power points installed with no fuss. Thanks Dan, you're a legend!

  • N
    Neil Smith
    a year ago

    Thanks to Dan for organising my job so promptly. Luke and Cooper are very pleasant young men, polite and professional, who did an excellent job. I would definitely recommend DM Electrical.

  • H
    Heather Rudkin
    8 months ago

    Excellent service provided on a timely basis which resolved a significant electrical issue at our home.

  • C
    Chase Burrows
    a year ago

    Amazing job, issue was fixed quickly and for good money. Good blokes too! Couldn't ask for anything better, definitely will be going back.